Vestas has secured a 59 MW order for two projects with Japanese wind power developer, Eurus Energy Holdings Corporation.
Vestas said the order includes supply and supervision of installation of 14 V117-4.2 MW wind turbines for the 21 MW Tabito and 38 MWÂ Sandaimyojin wind projects, to be located in Fukushima prefecture, Japan.
Vestas will also deliver a multi-year Active Output Management 4000 (AOM 4000) service agreement for the wind farm, providing a time-based availability guarantee to ensure optimised performance and long-term business case certainty for the customer.
Delivery of the turbines for Tabito project will begin in the third quarter of 2022, with commissioning scheduled for the second quarter of 2023. The delivery for Sandaimyojin project will begin in the second quarter of 2023, with commissioning planned for the first quarter of 2024.