Small Modular Reactors for AI Data Centers: Microsoft, Google, Amazon, Meta and Oracle Nuclear Projects, Costs and Timelines

X solar, wind, storage battery

X solar, wind, storage battery

Small modular reactors (SMRs) are emerging as a potential electricity source for artificial intelligence data centers as Microsoft, Google, Amazon, Meta and Oracle explore nuclear energy investments. Projects involving X-energy, Kairos Power, TerraPower, Oklo and other reactor developers could eventually deliver several gigawatts of low-carbon electricity, but construction costs, regulatory approvals, fuel availability and commissioning timelines remain major challenges.

AI data centers require continuous electricity for GPU clusters, cooling systems, networking equipment and supporting infrastructure. Unlike conventional enterprise computing facilities, large AI campuses can require hundreds of megawatts of power.

Nuclear energy offers reliable, low-carbon generation, making it attractive to technology companies seeking long-term electricity supplies.

However, most advanced SMR projects targeting AI infrastructure remain in development, demonstration or licensing stages.

Amazon, X-energy and AEP Plan 960 MW Nuclear Project in Indiana

Amazon, American Electric Power (AEP) and X-energy announced an agreement in October 2026 to evaluate a 960 MW advanced nuclear energy project in Sullivan County, Indiana.

The proposed facility would use 12 Xe-100 reactors, each capable of generating approximately 80 MW.

The project would be developed at a former coal power plant site, potentially benefiting from existing electricity infrastructure.

Amazon is providing development funding and intends to purchase electricity through a long-term agreement if the project advances to commercial operation.

According to the AEP nuclear project announcement, the project remains at the feasibility stage.

Amazon has also supported X-energy’s advanced reactor development through investment and commercial agreements.

Google and Kairos Power: 500 MW Nuclear Agreement

Google has entered into an agreement with Kairos Power to support deployment of multiple advanced nuclear reactors.

The arrangement targets up to 500 MW of electricity capacity by 2035, with initial deployment targeted around 2030.

Kairos Power is developing fluoride salt-cooled high-temperature reactors designed to support reliable electricity generation.

In April 2026, Kairos Power broke ground on its Hermes 2 demonstration project in Oak Ridge, Tennessee.

The facility is designed to supply up to 50 MW to the Tennessee Valley Authority electricity grid, supporting the regional power system serving Google data centers in Tennessee and Alabama.

The Kairos Power Hermes 2 construction announcement represents an important development milestone.

Meta and Oklo Target 1.2 GW Nuclear Campus in Ohio

Meta and Oklo have announced plans supporting the development of a nuclear energy campus in Pike County, Ohio.

The proposed facility could eventually deliver up to 1.2 GW of electricity generation capacity.

Oklo is developing advanced fast-reactor technology through its Aurora power platform.

The first phase has been targeted for deployment as early as 2030, with additional capacity potentially developed over subsequent years.

The proposed 1.2 GW capacity could support substantial AI computing demand, although electricity delivery will depend on project licensing, financing, fuel supply and construction.

Microsoft and Constellation: 835 MW Nuclear Restart

Microsoft’s nuclear energy strategy includes a major electricity procurement agreement with Constellation Energy.

The companies announced a 20-year power purchase agreement supporting the restart of Three Mile Island Unit 1 in Pennsylvania.

The reactor, renamed the Crane Clean Energy Center, has a generating capacity of approximately 835 MW.

The project was initially targeted for a 2028 restart, subject to regulatory approvals and technical requirements.

Unlike SMR developments, the Crane project involves restarting an existing conventional nuclear reactor.

This distinction is important because restarting an established plant presents different engineering and licensing challenges from constructing a first-of-a-kind advanced reactor.

Amazon and Energy Northwest: 320 MW Initial SMR Project

Amazon is also supporting an advanced nuclear project involving Energy Northwest and X-energy in Washington state.

The initial development concept involves four Xe-100 reactors with combined capacity of approximately 320 MW.

The development could expand to 12 reactors, delivering up to 960 MW.

Amazon’s involvement includes support for early project development and a potential long-term electricity purchase arrangement.

The project is designed to serve regional electricity demand, including growing data center requirements.

Google and Elementl Power: Three Nuclear Projects Totaling 1.8 GW

Google is also working with Elementl Power to develop three advanced nuclear energy projects in the United States.

Each proposed project would have a minimum generation capacity of 600 MW, representing at least 1.8 GW across the three sites.

Google is providing early-stage development capital and retaining the option to purchase electricity once the projects become operational.

Elementl Power is evaluating potential reactor technologies, construction partners and suitable locations.

The agreement expands Google’s nuclear strategy beyond Kairos Power and provides additional options for securing electricity for future AI infrastructure.

Meta and TerraPower: Up to 2.8 GW of Advanced Nuclear Capacity

Meta has agreed to support the development of up to eight TerraPower Natrium reactors.

The initial two units could provide 690 MW of firm electricity generation, with delivery targeted as early as 2032.

Meta also secured rights to electricity from up to six additional units, representing approximately 2.1 GW of capacity targeted for 2035.

Together, the eight potential reactors would provide approximately 2.8 GW of baseload generation.

TerraPower’s Natrium design combines a 345 MW sodium-cooled reactor with molten-salt energy storage capable of temporarily increasing output to 500 MW.

The first Natrium demonstration project in Wyoming received a construction permit from the U.S. Nuclear Regulatory Commission in March 2026.

Meta’s agreement with TerraPower demonstrates growing interest in nuclear projects capable of supplying multiple gigawatts rather than individual data centers.

Meta and Vistra: More Than 2.6 GW of Nuclear Electricity

Meta has also signed long-term electricity agreements with Vistra covering existing nuclear generation and planned capacity expansions.

Meta’s contract with Vistra indicates that the agreements involve the Perry and Davis-Besse nuclear plants in Ohio and the Beaver Valley facility in Pennsylvania.

Meta will purchase 2,176 MW of existing nuclear generation and support 433 MW of additional capacity through plant upgrades.

The combined contracted capacity reaches approximately 2,609 MW.

Electricity deliveries are scheduled to begin in late 2026, with additional capacity expected through 2034.

Meta’s nuclear agreements with Vistra, TerraPower and Oklo support up to 6.6 GW of existing and proposed nuclear capacity by 2035.

Oracle: Exploring Nuclear Power for Gigawatt AI Campuses

Oracle has identified nuclear energy as a potential long-term electricity source for large AI data centers.

Its infrastructure strategy increasingly involves campuses requiring hundreds of megawatts or approximately 1 GW of power.

SMR Construction Costs: What Could 300 MW Cost?

SMR investment requirements remain uncertain because commercial deployment experience is limited.

Consider a hypothetical 300 MW reactor project with an overnight construction cost of $8,000 per kilowatt.

Total construction expenditure would reach approximately $2.4 billion before financing, grid connections and additional development costs.

A 25 percent construction cost increase would raise expenditure to approximately $3 billion.

At a 90 percent capacity factor, a 300 MW plant would generate approximately 2.37 TWh annually.

A continuously operating 1 GW AI data center would consume approximately 8.76 TWh annually.

Delays Could Increase AI Data Center Electricity Costs

Project delays represent a major financial risk for nuclear-powered data centers.

A continuously operating 300 MW computing load consumes approximately 2.63 TWh annually.

If replacement electricity costs $100 per MWh more than the planned nuclear supply, the additional annual expenditure would reach approximately $263 million.

A two-year delay could increase replacement electricity expenditure by approximately $526 million under those assumptions.

India Plans ₹20,000 Crore Investment in Small Modular Reactors

India’s Nuclear Energy Mission has allocated ₹20,000 crore to support SMR research, development and deployment.

The programme includes the 220 MWe Bharat Small Modular Reactor, the 55 MWe SMR-55 and a high-temperature gas-cooled reactor concept.

Government estimates place the BSMR-200 project cost at approximately ₹5,960 crore.

Two SMR-55 units have an estimated combined project cost of ₹7,000 crore.

The government has indicated a construction period of approximately 60–72 months after the necessary administrative and financial approvals.

India’s SMR programme could eventually support industrial facilities, electricity networks and energy-intensive digital infrastructure.

However, the programme does not yet represent immediately available nuclear electricity for AI data centers.

Which Nuclear Projects Will Deliver Electricity First?

Existing nuclear plant agreements provide a more immediate route to securing low-carbon electricity than constructing new advanced reactors.

Meta’s Vistra agreements begin electricity deliveries in late 2026.

Microsoft’s Crane Clean Energy Center agreement initially targeted a 2028 reactor restart.

Google’s Kairos Power partnership targets initial commercial deployment around 2030, while the Hermes 2 demonstration is intended to establish technical and operational experience.

Oklo’s proposed Ohio campus targets initial deployment as early as 2030.

TerraPower’s first two Meta-supported units target delivery as early as 2032.

Amazon’s X-energy projects and Google’s Elementl Power developments remain dependent on regulatory approvals, financing and construction decisions.

Outlook: Nuclear Energy Becomes Part of AI Infrastructure Strategy

Microsoft, Google, Amazon and Meta are supporting nuclear energy through electricity purchase agreements, early-stage development funding and partnerships with reactor technology companies.

Their combined initiatives cover several gigawatts of existing and proposed nuclear generation.

For AI data center operators, SMRs represent a potentially important long-term electricity strategy, but grid capacity, conventional nuclear power, renewable energy and interim generation will remain essential while advanced reactors move toward commercial deployment.