TotalEnergies Acquires 450 MW Solar and 150 MW Battery Storage Project in UK from RES

TotalEnergies has acquired the Steeple Renewables Project in Nottinghamshire, England, from renewable-energy developer RES. The project comprises 450 MW of solar generation and a 150 MW battery energy storage system. Ownership of Steeple Solar Farm Limited transferred from RES UK & Ireland to TotalEnergies on October 31, with the acquisition reported on November 13. The development received a Development Consent Order in early October under the UK’s nationally significant infrastructure planning process. Located near the decommissioned West Burton Power Station, the project is designed to use existing electricity grid infrastructure in the area. The transaction adds a consented solar-plus-storage development to TotalEnergies’ UK renewable-energy portfolio.

ONDE and Tauron Plan 399 MW Wind and Solar Joint Venture in Poland

Polish renewable-energy developer ONDE signed a non-binding letter of intent with Tauron Zielona Energia on November 13 to establish a joint venture covering up to 399 MW of renewable-energy projects. The proposed portfolio comprises approximately 366 MW of onshore wind and 33 MW of solar capacity. Tauron plans to acquire a 50 percent stake in five project companies currently wholly owned by ONDE for an estimated €4.5 million–€5.4 million. The companies intend to develop the projects to ready-to-build status, after which Tauron could acquire the remaining stakes or both partners could sell the assets. Completion requires competition authority approval and definitive agreements.

Oyster Renewable Commissions 39.3 MWp Solar Capacity in ₹372 Crore Hybrid Project for Laurus Labs

Oyster Renewable Energy has commissioned the 39.3 MWp solar component of its 60.9 MW wind-solar hybrid project for pharmaceutical manufacturer Laurus Labs in Kadapa district, Andhra Pradesh. The project involves approximately ₹372 crore in investment and includes another 21.6 MW of wind capacity, scheduled for commissioning by December 2026. The operational solar installation is expected to generate 51.51 million units of electricity annually. Once the wind component is completed, combined generation is projected at 124 million units annually, with estimated carbon emissions reductions of 88,040 tonnes. Laurus Labs will consume the entire electricity output through a captive power arrangement and is targeting a 50 percent renewable-energy share by the fourth quarter of FY27.