How Much Does a 1 GW Wind Farm Cost in 2026? Onshore Investment Near $1 Billion vs $2.85 Billion Offshore

By Editor

Share

A 1 GW wind farm requires roughly $1 billion of investment for onshore development and around $2.85 billion for offshore wind based on global cost benchmarks. But turbine prices, foundations, transmission, financing, construction logistics and location can move the final investment substantially above or below these averages. In 2026, onshore wind remains one of the world’s cheapest sources of new electricity, while offshore wind offers higher capacity factors but requires much greater upfront capital.

The International Renewable Energy Agency’s cost data provides a useful starting point. Its 2024 global weighted-average total installed cost was $1,041/kW for onshore wind and $2,852/kW for offshore wind. For a 1 GW development, those figures translate into approximately $1.041 billion and $2.852 billion, respectively.

IRENA’s newer 2026 report shows that wind electricity costs continued improving in 2025, with global weighted-average levelized cost of electricity falling to $33/MWh for onshore wind and $78/MWh for offshore wind.

1 GW Wind Farm Cost: Onshore vs Offshore

The headline calculation is straightforward because 1 GW equals one million kW.

At $1,041/kW, a 1 GW onshore project costs about $1.041 billion, or $1.041 million per MW.

At $2,852/kW, a 1 GW offshore project costs about $2.852 billion, or $2.852 million per MW.

Offshore wind therefore carries an investment premium of approximately $1.81 billion per GW, based on these benchmarks.

The IRENA renewable power generation cost analysis confirms that renewables remain highly competitive: more than 90 percent of utility-scale renewable projects commissioned in 2025 generated electricity below the cost of the cheapest new fossil-fuel alternative in their respective markets.

Importantly, the $1.04 billion and $2.85 billion numbers are benchmarks rather than quotations for a specific 2026 project.

Turbines Can Represent 75 percent of Onshore Investment

Wind turbines are normally the largest component of an onshore project’s capital expenditure.

IRENA estimates that turbines represent around 75 percent of total installed onshore wind costs on average.

Applied to the $1.041 billion benchmark, that would imply an illustrative turbine-related investment of approximately $781 million, leaving around $260 million for other infrastructure.

The remaining investment covers items including:

turbine foundations and crane pads;

internal roads and site preparation;

electrical collection systems;

transformers and substations;

transmission and grid connections;

engineering and permitting;

transportation and construction; and

commissioning and contingencies.

A remote wind farm requiring new roads and long transmission connections can therefore cost significantly more than a project developed close to existing infrastructure.

1 GW Onshore Wind Cost Can Range From $727 Million to $2.11 Billion

One of the most important points for investors is the enormous variation between projects.

IRENA’s 2024 data put the fifth-percentile installed cost for onshore wind at approximately $727/kW, while the 95th percentile reached $2,110/kW.

For a 1 GW project, that translates into a range of roughly:

Low benchmark: $727 million

Global average: $1.041 billion

High benchmark: $2.11 billion

This spread demonstrates why cost-per-GW should never be used alone for investment decisions.

Terrain, wind resource, local manufacturing, labor, turbine specifications, permitting, financing and transmission requirements can all change the economics.

Turbine Size Changes the Project Budget

Larger turbines can reduce the number of machines required to build 1 GW.

A project using 5 MW turbines would need around 200 turbines, while an 8 MW configuration would require about 125 turbines.

Fewer turbines can mean fewer foundations, roads, electrical collection points and installation activities.

But bigger does not automatically mean cheaper.

Larger turbines require heavier components, bigger cranes, stronger foundations and more demanding transportation logistics. Developers therefore need to optimize the complete project rather than simply select the largest available turbine.

Why Offshore Wind Costs $2.85 Billion per GW

The offshore investment premium becomes clearer when the project is broken into components.

IRENA’s offshore cost analysis indicates that:

Turbines and towers: roughly 30-43 percent

Foundations: 13-22 percent

Electrical interconnection: 8-24 percent

Installation: 5-25 percent

Development: 2-9 percent

For a $2.852 billion project, turbines and towers alone could represent approximately $856 million-$1.23 billion, while foundations could represent around $371 million-$627 million.

Offshore projects also require inter-array cables, export cables, offshore substations, specialized ports and expensive installation vessels.

Distance from shore, water depth and seabed conditions can therefore materially change investment requirements.

Offshore Wind Offers Higher Capacity Factors

The higher offshore investment has to be considered alongside electricity production.

IRENA’s 2024 global weighted-average capacity factor for newly commissioned onshore wind was 34 percent, compared with 42 percent for offshore wind.

A 1 GW wind farm would theoretically generate approximately:

30 percent capacity factor: 2.63 TWh/year

35 percent: 3.07 TWh/year

40 percent: 3.50 TWh/year

45 percent: 3.94 TWh/year

The economics therefore depend on CAPEX per unit of lifetime electricity generated, not merely investment per MW.

A higher-cost project located in an excellent wind resource can potentially outperform a cheaper project with substantially lower annual production.

Wind Costs Continue to Fall in 2026

IRENA’s longer-term data show how dramatically wind economics have improved.

Global weighted-average onshore installed cost declined 55 percent from $2,324/kW in 2010 to $1,041/kW in 2024. Offshore wind declined 48 percent, from $5,518/kW to $2,852/kW.

IRENA’s previous cost outlook projected onshore wind total installed costs at approximately $960/kW in 2026, falling further to $861/kW by 2029. These are projections rather than observed 2026 global averages, so they should not replace project-specific budgets.

At the same time, IRENA’s latest observed data show onshore wind LCOE reaching $33/MWh in 2025, compared with $78/MWh offshore.

Adding 1 GWh Battery Storage Could Add Around $192 Million

Storage creates another potential investment layer.

IRENA’s 2024 global weighted-average utility-scale battery storage installed cost was approximately $192/kWh, down dramatically from $2,571/kWh in 2010.

At that benchmark:

500 MWh BESS: about $96 million

1 GWh BESS: about $192 million

These figures should only be used as indicative benchmarks. The complete investment depends on battery duration, MW rating, power conversion, controls, interconnection, cooling, fire protection, augmentation and civil works.

Storage can nevertheless improve wind economics where developers need to shift generation, manage transmission constraints or provide grid services.

Financing Is Becoming Critical to Wind ROI

A wind project’s physical construction cost is only one part of its economics.

Interest rates, debt-equity structure, construction duration and revenue certainty can materially change returns.

This issue is particularly important offshore because billions of dollars may be committed several years before the project begins generating revenue.

Europe provides an indication of the investment scale. It raised €9 billion to finance 5.2 GW of new wind projects in H1 2026, while installed capacity exceeded 311 GW. Europe is expected to add another 148 GW during 2026-2030.

The WindEurope 2026 investment and market outlook also highlights grids and permitting as major constraints on deployment.

Long-term PPAs and Contracts for Difference can reduce revenue uncertainty and financing costs, which can ultimately be as important as reducing turbine prices.

Offshore Wind Targets 30 percent Cost Reduction

The North Sea offshore wind industry has committed to reducing offshore wind costs by 30 percent by 2040 compared with 2025 levels, supported by scale, industrialization and lower financing costs.

North Sea governments are targeting 15 GW of offshore wind deployment annually between 2031 and 2040, alongside an investment framework intended to support manufacturing, ports, vessels and transmission.

The North Seas offshore wind investment pact highlights why future offshore economics will depend not just on bigger turbines but also on industrial scale, supply chains and cheaper capital.

What Really Determines the Cost of a 1 GW Wind Farm?

For investors evaluating a wind project in 2026, the most useful starting benchmarks are around $1.04 billion for 1 GW onshore and $2.85 billion offshore.

But the investment decision should focus on six variables: turbine and equipment costs, wind resource and capacity factor, civil and foundation costs, grid connection and transmission, financing, and expected lifetime generation.

Offshore projects add another layer of exposure through subsea cables, ports, vessels and marine construction.

The central investment question is therefore not simply how much does 1 GW of wind cost?

It is how much electricity that $1 billion-$3 billion investment can reliably produce over its operating life — and at what financing, grid and operating cost.