Share

Shanghai Electric has started commercial operations of Block B in phase five at Mohammed bin Rashid Al Maktoum Solar Park (MBR Phase V) facility in Dubai.

The equipment started producing electricity for commercial use on 10 October, 17 days earlier than expected.

The project is divided into three blocks – A, B and C, each with a capacity of 300 MW. Block A was put into full operation in July 2021. The design for Block C has been provisionally completed, meaning that preparations for its construction, including equipment deliveries, and the laying of underground cables, are in full swing.